例题:

1What system is a part of the project management information system (PMIS)?

A. Configuration management

B. Communication management

C. Change management

D. Contract change control

什么系统属于项目管理信息系统(PMIS)的组成部分?

A.配置管理

B.沟通管理

C.变更管理

D.合同变更控制

参考答案:A

2A project manager is managing a systems project across multiple countries. In project progress meetings, the project manager realizes that project team members across these various location are not aligned on progress, which may impact dependencies.

What should the project manager do address this?

A. Appoint sub-project managers to do weekly project status updates for each location

B. Assign work so each location does not need to interact with the other

C. Use a common project management information system (PMIS)

D.Colocate all project team members

项目经理正在管理一个跨越多国的系统项目。在项目进度会上,项目经理发现这些不同地理位置的项目团队成员进度各不一致,而这可能影响依赖关系为解决这种情况,项目经理应该怎么做?

A.指定子项目经理为每个地理位置执行每周项目状态更新

B.分配工作,让每个地理位置都不需要与其他地理位置互动

C.使用一个共同的项目管理信息系统(PMIS)

D.让所有项目团队成员集中办公

参考答案:C

解析:使用共同的PMIS,保持绩效信息的更新。

项目管理信息系统提供下列工具:进度计划工具、工作授权系统、配置管理系统、信息收集与发布系统,或进入其他在线自动化系统的网络界面。本系统也可用于自动收集和报告关键绩效指标。